Rocks Railway Restoration
February 2006
Weekly progress diary from beginning of March 05
made some of the steps safer at the bottom station,
started digging out the trench between the bottom water tank
Trench full of dead rotten wood
Nott's signature
Made part of the first floor of bottom station safer- bit dusty, and joists rather rotten.
The rest of the floor is concrete since the Crossley engines were up here.
started preparing the back door of the top station for painting.